How To Generate S-Curve based on Labor Units in Primavera!
1) S-Curve Based on Labor Unit
Step 1 : Establish your Resources Database. Click to Enterprise -> Resources

Step 2 : Key in your Resources i.e. Labor (Project Director, Project Manager, Planner, Engineer, Supervisor etc). You may arrange according to their Organization Chart or Organization Breakdown Structure (OBS). Don’t forget to key in Calendar for each Resources, their cost per hour, overtime factor etc.


Step 3 : Go to Activities tab again, open Add Resources tab at the bottom & key in Resources for each activity i.e. Land Surveyor for Site survey activity etc.

Step 4 : Go to Activity Usage Profile at the top and click on it. As you can see below, you’ve generate your S-curve table based on Labor units!

Step 5 : you can drag sliding bar to the left & up to get maximum size of your s-curve.